Construction at Tower B is progressing steadily across multiple levels, with significant advancements in both structural and finishing works. Exterior paint work for the swimming pool has been successfully completed, enhancing the overall external aesthetics. Several units, including 202-B and 302-B, have reached advanced stages with plastering, false ceiling framework, window installation, balcony railings, floor tiling, and staircase steel framework fully completed. Units such as 301-B, 401-B, 402-B, and 502-B are nearing completion, with tiling work almost finished and key structural and interior elements in place. In unit 503-B, major milestones have been achieved, including installation of kitchen cabinets, platforms, and doors, indicating readiness for final finishing stages. Higher-level units from 501-B through 901-B are progressing well, with plastering, ceiling frameworks, tiling, and staircase work underway. Overall, the project is moving forward as planned, with multiple units transitioning from structural work to interior finishing, reflecting consistent progress toward completion.