The construction project is progressing well, with several key areas nearing completion. In the Walk-In Wardrobe 1, the floor tiling, plastering, wall moulding, doors, and switch boards are all fully installed. The Living Room has seen similar progress with completed floor tiling (including the balcony), wall plastering and moulding, finished doors, switch boards, and a painted ceiling. Additionally, the Internal Entrance Staircase is structurally complete, with glass anchored into place and steps installed. The Entrance Area is also nearly finished, with installed duct windows, anchored pipes, and a completed wall painting. The Master Bedroom and Bedroom 2 have both seen floor tiling, plastering, wall moulding, and ceiling painting completed, along with doors, switch boards, and windows installed. In the Kitchen, floor tiling and balcony railings are done, along with installed cabinets, door jambs, and windows. The Level 1 Passage and Master Bedroom Toilet are progressing, with switch boards installed, and tiling and plastering largely complete. Civil Work across the site, including walls, planter bed walls, and steps, has been completed, though some finishing work, such as floor tiling and steps finishing, is still ongoing. The Swimming Area is also mostly done, with floor tiling, skirting, and wall plastering completed. For the Wings A and B, façade moulding and painting are near completion, with scaffolding removed in Wing A, while Wing B still awaits the removal of scaffolding. The Terrace has installed skylights, windows, and completed tiling, with planter beds in place. Overall, while many tasks are completed, a few areas still require finishing touches, particularly in plastering, railings, and tiling.