Construction Progress Update: Finishing Works Advancing Steadily Across Key Areas

Project Name

Habitat 854

Location

Kulambiro, Kampala

Date

June 19, 2025

Significant progress continues across various areas of the project, with multiple finishing works nearing completion:

  • Common Passage Wall: First coat of paint has been successfully applied, marking a key step in interior finishing.

  • Common Passage Railing: Application of DU black paint is ongoing, with approximately 85% of the work completed.

  • Common Staircases S1 & S2: Tiling work is nearly complete, currently at 98%, enhancing accessibility and aesthetics.

  • Windows and Doors: Glazing installation is underway and has reached 50% completion, contributing to the building’s overall enclosure and weatherproofing.

What is it for?

The construction work is progressing steadily, with multiple finishing activities advancing across key areas of the site. The first coat of paint has been successfully applied on all common passage walls, setting the stage for final interior finishes. Simultaneously, the application of DU black paint on the common passage railings is ongoing and has reached approximately 85% completion, adding to the visual appeal and safety of the space. Tiling in common staircases S1 and S2 is almost complete at 98%, with only minor edge and corner finishes pending. Glazing work for windows and doors is progressing well, currently at 50%, and is being executed in coordination with frame installation to maintain quality and alignment. Electrical fittings and plumbing fixtures are being installed in tandem with the finishing works to streamline timelines. Internal wall preparation, including putty and primer application, is underway in several areas, ensuring surfaces are ready for final coats. Overall, with major structural and service works completed, the project is now in the final phase of execution, with a strong focus on delivering high-quality finishes and meeting project handover deadlines.

HABITAT 854

Why does it matter to you?

Finishing works are progressing well across key common areas. The first coat of paint has been applied to the common passage walls, and the application of DU black paint on the common passage railings is 85% complete. Tiling work in common staircases S1 and S2 is nearly finalized, with 98% completion, marking significant progress toward the final stages of the project.

Images of construction.

The ultimate benefits.

The ultimate benefits of the ongoing finishing works include enhanced aesthetic appeal, improved safety, and increased functionality of common areas. The painted passage walls and DU black-painted railings contribute to a clean, modern look while ensuring durability and corrosion resistance. Nearly completed staircase tiling not only elevates the visual finish but also provides better grip and long-term ease of maintenance. Collectively, these improvements enhance user experience and move the project closer to final delivery and occupancy readiness.

Share this information with your family or friends;

WhatsApp
Facebook
Twitter

Respond to this post.

Project Name

Habitat 854

Location

Kulambiro, Kampala

Date

June 19, 2025

Visit Our Site

Get the best sustainable homes in Kampala.

Everything is closer to home

Free Brochure!

You’ll get a detailed design, overview,
location, apartment, and more…

You’ll get a detailed design, overview, location, apartment, and more…

HABITAT 854

Book Free Appointment

Visit the construction site to see the progress in real time and get an overview of the project.
Visit the construction site to see the progress in real time and get an overview of the project…

HABITAT 854

This website uses cookies to ensure you get the best experiacne on our website.
Aesthetic Developers

Get In Touch with us !

Kindly fill out the quick form and we will be in touch with lightning speed.

Secured By miniOrange