Podium slab casting is currently in progress, establishing a structural connection between Wing A and Wing B. In Wing A, significant progress has been made with the completion of the skylight installation and ongoing window shutter fixing. Preparations for tiling have also begun, with terrace cleaning underway. Meanwhile, in Wing B, the water tank has been successfully casted, and work on the terrace parapet is actively in progress.