Kampala highlights steady construction advancement, with major activities including rock breaking, plum concrete works, formwork, steel reinforcement fixing, and concrete casting. Several tasks like rock breaking, steel fixing, and column casting exceeded planned targets, while others continued as scheduled. The workforce totaled 56 personnel, and key site equipment remained operational. Challenges like heavy rainfall and pending design approvals were noted, with solutions proposed for site protection and coordination. The report also included site inspections, safety observations, and plans for upcoming activities like formwork and reinforcement for first-floor works.